New Water Treatment Plant

Located on the shores of Constance Lake near Hearst, Ontario

Project Scope

Year: 2015–2016
Client: Constance Lake First Nation
Project Scope Performed Under: Mahiihkanuk Nuna/Tribury Joint Venture, a partnership of Nuna Logistics Limited, Mahiihkanuk Construction Limited Partnership (MFN), and Tribury Construction (1995) Inc.

 

Constance Lake First Nation commissioned a new water treatment plant, including treatment equipment, connection to existing communal system, and partial decommissioning of the existing water treatment plant. Generally, the new water treatment plant included pre-engineering building and foundation/reservoir, filters, pumps, chemical feed equipment, natural gas emergency generator, HVAC, electrical, and controls.

Services provided included the following.

  • Excavation of backfill for the new water treatment plant
  • Installation of site services (water, storm, and sanitary sewer)
  • New pavement structure